The 75/24 Split (pronounced "seventy-five twenty-four split"), also commonly known simply as "The Split", is the name given to the interchange between Interstates 75 and 24 in Chattanooga, Tennessee. The interchange was originally constructed between 1959 and 1961 as a simple directional-T interchange. Although Chattanooga is only a mid-sized city by national standards, the interchange is the convergence point of two major north-south freight corridors, running between Atlanta and Detroit, and Atlanta and Chicago, respectively. As a result, the interchange has been ranked as one of the most congested bottlenecks in the country, rendering its original design obsolete, and has become notorious for congestion and accidents. The interchange is currently undergoing extensive reconstruction in two phases.

75/24 Split
Map
Location
Chattanooga, Tennessee
Coordinates35°0′16″N 85°12′48″W / 35.00444°N 85.21333°W / 35.00444; -85.21333
Roads at
junction
Construction
TypeSemi-directional T interchange
Constructed1959-1961
OpenedMay 31, 1961 (1961-05-31) (partial)
December 7, 1962 (full)
Maintained byTennessee Department of Transportation

Overview edit

Description edit

 
The approach to the Split on I-75 southbound in 2005, prior to reconstruction.

The interchange is located along the border between the southeastern part of Chattanooga and East Ridge, a suburb of the former, approximately one mile (1.6 km) north of the Georgia state line. It serves as the eastern terminus of I-24 at I-75. It is exit 2 on I-75 and exits 185 A and B on I-24. It is located directly south of Eastgate Towne Center and west of Camp Jordan, a large multi-use park operated by the city of East Ridge. The area to the west of the interchange comprises mostly residential neighborhoods. The interchange is also located less than one mile (1.6 km) south of the Chattanooga Metropolitan Airport. I-75 crosses West Chickamauga Creek directly south of the interchange and South Chickamauga Creek east of it; the two creeks converge along the boundary of Camp Jordan.[1]

The interchange is a semi-directional T configuration, with I-75 shifting from a northwest-to-southeast alignment toward Atlanta to a northeast-to-southwest alignment toward Knoxville. I-24 continues in an east-west alignment past the interchange, first toward Downtown Chattanooga, and ultimately north to Nashville. I-75 carries three lanes in each direction through the interchange, with both ramps coming from I-24 also carrying three lanes. The ramp from I-75 southbound to I-24 westbound has two lanes, and the ramp from I-75 northbound to I-24 westbound bottlenecks from two to one lane; both of these ramps will be expanded to three lanes once the second phase of reconstruction is complete. A barrier-separated collector-distributor slip ramp along I-75 northbound also provides direct access to I-75 northbound and I-24 westbound from US 41 and the Tennessee Welcome Center directly to the south in order to reduce weaving. On northbound I-75, the interchange is signed as I-24 westbound to Chattanooga and Nashville, while from southbound I-75, it is signed for I-24 to I-59 to Chattanooga and Birmingham, Alabama.[1]

Traffic and congestion edit

The Split serves as the convergence point of two major freight corridors that run between Atlanta and Detroit and Atlanta and Chicago, respectively. For this reason, the interchange and much of I-24 through Chattanooga receives an extremely high volume of through truck traffic, which results in the city experiencing unusually severe traffic congestion for its size. A 2015 study by Cambridge Systematics found that 80 percent of the trucks that pass through Chattanooga are destined for a different location, the highest share of any metropolitan area in the country, and identified the Split as one of the worst bottlenecks in the region.[2] Another study that same year by the Texas A&M Transportation Institute ranked Chattanooga the second-most congested city of its size in the country.[3] The American Transportation Research Institute ranked the Split the seventh worst bottleneck in the United States for trucks in 2021, and the 10th worst in 2022.[4][5] The Split fell to number 59 in 2023 after the first phase of its reconstruction was completed.[6]

History edit

Construction and early history edit

 
1955 Bureau of Public Roads highway plan for Chattanooga
 
The Split shortly after construction was completed, looking east

The 75/24 Split, along with both Interstates, were part of the original stretches of Interstate Highways authorized by the Federal-Aid Highway Act of 1956. On July 26, 1959, the contract to construct the interchange, along with the stretch of I-75 extending to the Georgia state line, was awarded to Oman Construction of Nashville.[7][8] The interchange was dedicated on May 31, 1961, in a ceremony officiated by state highway commissioner D. W. Moulton, Chattanooga Mayor P. R. Olgiati, and Hamilton County Judge (now County Mayor) Chester Frost. The interchange cost US$3.32 million (equivalent to about $34M in 2023), and was one of the first sections of both I-75 and I-24 to be completed in Tennessee.[9] Referred to at the time as the Spring Creek Interchange, the interchange was constructed in a simple directional-T configuration, with ramps to and from I-24 connecting to I-75 northbound from the left. When first opened, I-75 north of and I-24 west of the interchange were not yet complete; traffic heading in the direction of I-24 westbound had to use temporary connections to Spring Creek Road, and I-75 northbound traffic had to turn around at South Chickamauga Creek. In late October 1962, I-24 was extended approximately 2 miles (3.2 km) to Belvoir Avenue,[10] and on December 7, 1962, the 2.1-mile (3.4 km) section of I-75 between the Split and SR 320 (East Brainerd Road) opened, which also opened the remaining ramps on the interchange.[11]

Between its initial construction and eventual reconstruction, the interchange changed little from its original configuration, although I-75 was widened to six and eight lanes south of the interchange in the late 1980s and from four to eight lanes north of the interchange in the early 1990s.[12] As traffic increased in the succeeding decades, the configuration of the Split gradually became inadequate. The ramp between I-75 northbound and I-24 westbound, which reduced from two lanes to one, became a pronounced bottleneck, and sharp curves in the interchange became more hazardous, especially for trucks.[13]

Reconstruction edit

 
Approaching the Split on I-75 southbound in the rain on December 22, 2019

By the 2000s, the Split had become obsolete, and in November 2012, TDOT unveiled a concept to reconstruct the entire interchange, expected to cost more than $100 million.[13] After the Tennessee General Assembly passed the IMPROVE Act in 2017, which increased the state's fuel taxes and vehicle registration fees with the intent of funding a backlog of 962 needed transportation projects, reconstruction of the Split became a top priority.[14] However, the final design ended up being far more complex than initial concepts, requiring the project to be split into two phases.[15]

 
Reconstruction activities along I-75 over South Chickamauga Creek approaching the Split on January 31, 2021

On December 21, 2018, TDOT awarded a design-build contract for the first phase of the reconstruction at a cost of $132.6 million (equivalent to about $161M in 2023) to C.W. Matthews Contracting of Marietta, Georgia.[16][17] The first phase involved reconfiguring most of the interchange. I-75 was reconstructed as a straighter six-lane mainline through the interchange, with all left-hand movements removed, and both ramps from I-24 eastbound were widened to three lanes, with the one connecting to I-75 northbound reconfigured to become the top level of the interchange. A collector–distributor facility that carries traffic directly from US 41 and the Tennessee Welcome Center along I-75 southbound was constructed, providing direct access to both I-75 southbound and I-24 westbound. Both ramps from I-75 to I-24 were left in their original lane configurations, but additional space was provided to widen them to three lanes in the second phase. The overpasses on Spring Creek Road directly west of the interchange were also rebuilt to allow for additional lanes on I-24 in the second phase.[18] On April 1, 2019, weeks before the reconstruction project began, part of the bridge on I-75 southbound over the ramp from I-75 northbound to I-24 westbound collapsed, injuring one person and blocking traffic for hours.[19][20][21] TDOT's chief engineer said that the collapse was most likely caused by weakening of the bridge's rail that occurred when an illegally oversized load hit the bridge.[22] Preliminary work on phase 1 began in May 2019,[23] and the project was completed on August 19, 2021, slightly over contract at a cost of $133.5 million.[24]

After the first phase was completed, the two-to-one lane bottleneck on the ramp from I-75 northbound to I-24 westbound was left in place for the second phase, a decision which received criticism.[25] In preparation for the second phase, the Belvoir Avenue overpass and Germantown Road underpass were replaced in a $32.4 million project between May 2020 and August 2021.[26] The latter replacement utilized accelerated bridge construction by shifting I-24 traffic onto the Germantown Road entrance and exit ramp and the adjacent North and South Terrace Roads, two frontage roads on both sides of I-24, for three weekends between April and June 2021.[27]

On November 28, 2022, TDOT awarded the contract for the second phase to Wright Brothers Construction of Charleston, Tennessee, for $162 million.[28] The project consists of reconstructing and widening I-24 between the interchange and Germantown Road, which will initially require the replacement of the McBrien Road and Moore Road overpasses. This stretch of I-24, which is currently three lanes in each direction, will be expanded to four lanes in each direction, in addition to new auxiliary and merge lanes between Moore Road and the Split. The orientation of the ramps at the Belvoir Avenue/Germantown Road interchange will also be reversed to reduce weaving, and the widening of this section will allow for all of the ramps in the Split to be expanded to three lanes. The section of I-75 between approximately 1.5 miles (2.4 km) east of the Split and SR 320 will also be widened from four to five lanes in each direction, and a railroad overpass along this section will be replaced and raised.[29][30] Final design work began in the spring of 2023, and construction began on July 13, 2023.[31][32][33]

References edit

  1. ^ a b DeLorme (2017). Tennessee Atlas & Gazetteer (Map) (2017 ed.). 1 in:2.5 mi. Yarmouth, Maine: DeLorme. ISBN 978-1946494047.
  2. ^ Pare, Mike (February 15, 2015). "Forget trains. Chattanooga is No. 1 in the nation for truck traffic". Chattanooga Times Free Press. Retrieved January 11, 2022.
  3. ^ Pare, Mike (August 28, 2015). "Chattanooga traffic gridlock sets new records". Chattanooga Times Free Press. Retrieved February 26, 2023.
  4. ^ Peña, Samuel (December 14, 2021). "Tennessee making effort to improve I-75/I-24 split ranked as 7th worst bottleneck in U.S." WTVC. Chattanooga. Retrieved May 17, 2023.
  5. ^ "The Nation's Top Truck Bottlenecks - 2022" (PDF). American Transportation Research Institute. February 9, 2022. Retrieved May 16, 2023.
  6. ^ "Chattanooga, TN: I-75 at I-24" (PDF). Washington, D.C.: American Transportation Research Institute. February 7, 2023. Retrieved May 17, 2023.
  7. ^ Report of the State Highway Commissioner of Tennessee for the Biennium Ending June 30, 1960 (Report). Nashville: Tennessee Department of Highways. 1960. p. 80. Retrieved November 12, 2023 – via HathiTrust Digital Library.
  8. ^ "Program Is Set At Spring Creek". The Chattanooga Times. May 30, 1961. p. 3. Retrieved February 26, 2023 – via Newspapers.com.
  9. ^ Munck, Hal (June 1, 1961). "Spring Creek Interchange Dedicated by Road Chief". The Chattanooga Times. pp. 3, 14. Retrieved February 26, 2023 – via Newspapers.com.
  10. ^ "One Section of Freeway Opened, Another Soon to Be (photos)". Chattanooga Daily Times. October 27, 1962. p. 3. Retrieved February 26, 2023 – via Newspapers.com.
  11. ^ Gibson, Springer (December 6, 1962). "East Brainerd Freeway Readied". Chattanooga Daily Times. pp. 1, 5. Retrieved February 26, 2023 – via Newspapers.com.
  12. ^ Tennessee Department of Transportation. "1987–1991 Contract Awards" (PDF). Tennessee Department of Transportation. Archived (PDF) from the original on January 24, 2020. Retrieved July 7, 2020.
  13. ^ a b Walton, Judy (November 12, 2012). "The big rebuild: Tennessee eyes $100 million redesign of I-75/24 split". Chattanooga Times Free Press. Retrieved March 23, 2023.
  14. ^ "Transportation Commissioner: I-24/I-75 split considered "worst intersection" in state". Chattanooga: WTVC-TV. November 9, 2017. Retrieved March 23, 2023.
  15. ^ "Interstate 75 Interchange at Interstate 24 - Phase II - Frequently Asked Questions". Tennessee Department of Transportation. 2022. Retrieved March 23, 2023.
  16. ^ "TDOT: I-24/I-75 interchange project to begin in 2019, last less than 3 years". Chattanooga: WTVC-TV. December 21, 2018. Retrieved December 7, 2019.
  17. ^ Benton, Ben (May 6, 2019). "Contractor starts early work, materials deliveries at I-75/I-24 'Split'". Chattanooga Times Free Press. Retrieved December 7, 2019.
  18. ^ "Interstate 75 Interchange at Interstate 24 - Phase I". Nashville: Tennessee Department of Transportation. 2018. Retrieved August 23, 2021.
  19. ^ Vera, Amir (April 1, 2019). "Concrete bridge railing collapses onto Tennessee interstate, injuring one person". CNN. Retrieved April 1, 2019.
  20. ^ "Bridge collapses on I-75 in Chattanooga; roadways still blocked hours later". Atlanta: WSB-TV. April 1, 2019. Retrieved April 1, 2019.
  21. ^ "Part of I-75 bridge collapses onto road in Chattanooga, TN". Newport, Kentucky: WXIX-TV. April 1, 2019. Archived from the original on April 2, 2019. Retrieved April 1, 2019.
  22. ^ Pace, Mark (April 3, 2019). "Here's what likely caused the railing to collapse on the I-75 bridge in Chattanooga". Chattanooga Times Free Press. Retrieved April 3, 2019.
  23. ^ Benton, Ben (May 6, 2019). "Contractor starts early work, materials deliveries at I-75/I-24 'Split'". Chattanooga Times Free Press. Retrieved December 7, 2019.
  24. ^ Benton, Ben (August 22, 2021). "Phase 1 of Split project crosses finish line, but bottleneck from I-75 North to I-24 will linger". Chattanooga Times Free Press. Retrieved August 23, 2021.
  25. ^ Benton, Ben (June 16, 2021). "I-75 bottleneck at I-24 likely to continue until last new lanes complete". Chattanooga Times Free Press. Retrieved May 16, 2023.
  26. ^ "TDOT to Begin Bridge Replacement Project on Interstate 24 in Chattanooga" (Press release). Tennessee Department of Transportation. April 15, 2020. Archived from the original on May 13, 2022. Retrieved May 13, 2022.
  27. ^ Parker, Collins (April 28, 2021). "TDOT will close I 24 at Germantown again this weekend for bridge replacement". Chattanooga: WDEF-TV. Retrieved March 23, 2023.
  28. ^ Benton, Ben (December 1, 2022). "$161 million low bid awarded for next phase of Chattanooga's I-75/I-24 'split' project". Chattanooga Times Free Press. Retrieved May 17, 2023.
  29. ^ "Interstate 75 Interchange at Interstate 24: Phase II". Tennessee Department of Transportation. Retrieved May 17, 2023.
  30. ^ Williams, Brianna (December 16, 2021). "Updates on Chattanooga's highway + interstate projects". Nooga Today. Chattanooga. Retrieved May 17, 2023.
  31. ^ "Interstate 75 Interchange at Interstate 24: Phase II; Timeline". Tennessee Department of Transportation. Retrieved May 17, 2023.
  32. ^ Benton, Ben (July 13, 2023). "Phase 2 of I-75/I-24 split project gets underway with bridge closures in Hamilton County". Chattanooga Times Free Press. Retrieved December 9, 2023.
  33. ^ Davis, Jaclyn (July 17, 2023). "Starting Wednesday: Detours to go up in next phase of I-24/I-75 split construction in Chattanooga". WTVC. Chattanooga. Retrieved December 9, 2023.